Tender number | RBI/Hyderabad/Estate/277/23-24/ET/376 |
Date of publication of NIT | Aug 29, 2023 |
Nature of work | Renovation of 2nd Floor Lobby, Main Office Building, RBI, Hyderabad |
Mode of tender enquiry | E-Tender |
Type of bidding (single/two bid system) | Two Bid System |
Last date of receipt of tender | Sep 26, 2023 |
Number of tenders received | 3 (Three) |
Nos. and names of parties qualified after technical evaluation | 3 (Three) 1. M/s. A N Satyanarayana
2. M/s. M Srinivas and Brothers
3. M/s. Virtue Interior Designers and Contractors |
Nos. and names of parties not qualified after technical evaluation | -
|
Commercial Bid Ranking, if any | |
Final Ranking, if any | |
Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
Contract number and date | HYD.ESTT.GEN.No.S157/03-02-055/2023-2024 dated Oct 11, 2023 |
Name of contractor | M/s. M Srinivas and Brothers |
Value of contract | ₹12,03,475/- |
Scheduled date of completion of supplies | Dec 20, 2023 |
Actual date of start of work | Oct 21, 2023 |
Actual date of completion of work | Jan 29, 2024 |
Reasons for delay, if any | There is a total delay of 40 days in completion of the work out of which delay of 07 days is attributable to the vendor for which liquidated damages have been imposed. |