| Tender number | RBI/Bhubaneswar Regional Office/Estate/29/24-25/ET/841 |
| Date of publication of NIT | Jan 28, 2025 from 18:00 hrs onwards |
| Nature of work | Renovation (Electrical Works) of Third Floor Area, Main Office Building, RBI, Bhubaneswar |
| Mode of tender enquiry | e-Tender on MSTC website |
| Type of bidding (single/two bid system) | Two Bid system |
| Last date of receipt of tender | Feb 13, 2025 till 14:00 Hrs. |
| Number of tenders received | 2 (Two) i. M/s Vee Jay Engineers ii. M/s Khusi Enterprises |
| Nos. and names of parties qualified after technical evaluation | 2 (Two) i. M/s Vee Jay Engineers
ii. M/s Khusi Enterprises |
| Nos. and names of parties not qualified after technical evaluation | NA
|
| Commercial Bid Ranking, if any | NA |
| Final Ranking, if any | NA |
| Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
| Contract number and date | BBS.ESTT.ESAD.No. S784/03-02-006/2024-2025 dated Feb 24, 2025 |
| Name of contractor | M/s Khusi Enterprises |
| Value of contract | ₹30,70,770/- |
| Scheduled date of completion of supplies | Within 30 days from the 10th day of issue of the work order i.e. April 04, 2025 |
| Actual date of start of work | Mar 07, 2025 |
| Actual date of completion of work | Jun 09, 2025 |
| Reasons for delay, if any | Due to delay in electrical works such as raceways, ducting etc. the site could not be released to the civil vendor within time. As the civil work could be commenced only after receipt of the site with a delay, the work could not be completed within the stipulated time and had to be extended. After completion of civil works, installation of workstations could be taken up and thus the electrical works such as providing connections to workstations have been delayed. |