| Tender number | RBI/Mumbai Regional Office/Estate/144/24-25/ET/844 |
| Date of publication of NIT | Jan 30, 2025 |
| Nature of work | Providing and Fixing EPDM Rubber Flooring in Children’s Play Area at RBI Quarters, Santacruz (Officers’ side), Santacruz West, Mumbai |
| Mode of tender enquiry | E-Tender |
| Type of bidding (single/two bid system) | Two Part Tender |
| Last date of receipt of tender | Feb 20, 2025 |
| Number of tenders received | 6 (Six) |
| Nos. and names of parties qualified after technical evaluation | 6 (Six) 1. M/s Aakar Shilp
2. M/s Mohd Altaf Hanif Qureshi
3. M/s Bharati Enterprises
4. M/s Balaji Construction
5. M/s Vaishnadevi Furnishers
6. M/s G S Interior |
| Nos. and names of parties not qualified after technical evaluation | -
|
| Commercial Bid Ranking, if any | 1. M/s Aakar Shilp
2. M/s Mohd Altaf Hanif Qureshi
3. M/s Bharati Enterprises
4. M/s Balaji Construction
5. M/s Vaishnadevi Furnishers
6. M/s G S Interior |
| Final Ranking, if any | 1. M/s Aakar Shilp
2. M/s Mohd Altaf Hanif Qureshi
3. M/s Bharati Enterprises
4. M/s Balaji Construction
5. M/s Vaishnadevi Furnishers
6. M/s G S Interior |
| Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
| Contract number and date | MRO.ESTT.EST-BY.No.2065/00-08-001/2024-2025 Date - Mar 12, 2025 |
| Name of contractor | M/s Aakar Shilp |
| Value of contract | ₹12,01,387.50/- |
| Scheduled date of completion of supplies | The time allowed for completion of the work is 2 months from the 10th day of work order. |
| Actual date of start of work | Mar 22, 2025 |
| Actual date of completion of work | Jun 03, 2025 |
| Reasons for delay, if any | 1. Due to non-removal / re-installation of Kids play equipment delay happens
2. Due to monsoon period, the work got delayed. |