Table 35 : Sector-Wise Cost Overrun of Delayed Central Sector Projects (End-March)
(End-March)
(₹ Crore)
Sector / Year 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1. Atomic energy                            
a) Number of projects 3 4 3 4 4 4 4 4 4 4 4 3 3 3
b) Original estimate 17769 38056 36950 40442 40442 40442 40442 67120 67120 67120 67120 27271 27271 27271
c) Now anticipated 22607 40709 41049 46726 51918 51918 52241 69728 75589 80348 80348 43139 43969 47266
d) Cost overrun 4838 2700 4100 6284 11476 11476 11799 2608 8469 13228 13228 15868 16698 19995
2. Civil aviation                            
a) Number of projects 3 3 3 3 5 1 3 1 1 4 11 4 6 8
b) Original estimate 2420 2588 2588 989 1659 309 842 315 315 3235 8527 3288 3834 4825
c) Now anticipated 2420 2970 2970 1042 1712 309 1239 441 441 3362 8641 4358 6391 8628
d) Cost overrun 0 400 400 53 53 0 397 127 127 127 114 1070 2556 3803
3. Coal                            
a) Number of projects 10 19 28 30 37 42 35 37 37 42 55 9 8 8
b) Original estimate 5851 13791 24263 26241 28302 23987 19120 20254 21142 23769 76470 28083 27219 23239
c) Now anticipated 7541 15102 26137 36435 32310 25308 19022 20473 22274 29117 72521 33167 33110 29057
d) Cost overrun 1690 1300 1900 10194 4008 1322 -98 219 1133 5348 -3949 5084 5890 5818
4. Finance                            
a) Number of projects 0 0 0 0 0 0 0 0 0 0 1 0 1 1
b) Original estimate 0 0 0 0 0 0 0 0 0 0 209 0 209 209
c) Now anticipated 0 0 0 0 0 0 0 0 0 0 209 0 262 262
d) Cost overrun 0 0 0 0 0 0 0 0 0 0 0 0 53 53
5. Fertilisers                            
a) Number of projects 1 2 1 0 0 0 1 2 1 5 4 0 0 0
b) Original estimate 1479 763 1479 0 0 0 198 681 198 1299 1101 0 0 0
c) Now anticipated 1479 763 1479 0 0 0 209 692 209 1311 1101 0 0 0
d) Cost overrun 0 0 0 0 0 0 12 12 12 12 0 0 0 0
6. Mines                            
a) Number of projects 1 0 0 0 0 0 0 0 0 2 3 3 3 3
b) Original estimate 4092 0 0 0 0 0 0 0 0 5707 6738 6429 4992 4992
c) Now anticipated 4402 0 0 0 0 0 0 0 0 5703 6738 7684 6303 7280
d) Cost overrun 310 0 0 0 0 0 0 0 0 -3 0 1255 1311 2288
7. Steel                            
a) Number of projects 7 10 15 13 17 15 19 15 10 8 6 1 2 1
b) Original estimate 30280 51099 64698 64208 56371 39095 41294 46113 26774 25965 19922 15525 17618 2093
c) Now anticipated 39780 57158 70856 70162 59940 39601 41521 45901 33578 33222 26337 21940 26062 2719
d) Cost overrun 9500 6100 6200 5954 3569 505 227 -213 6804 7257 6415 6415 8444 626
8. Petro-chemicals                            
a) Number of projects 0 0 1 0 1 0 0 0 0 0 0 0 0 0
b) Original estimate 0 0 5461 0 5461 0 0 0 0 0 0 0 0 0
c) Now anticipated 0 0 8920 0 9834 0 0 0 0 0 0 0 0 0
d) Cost overrun 0 0 3500 0 4373 0 0 0 0 0 0 0 0 0
9. Petroleum                            
a) Number of projects 27 38 39 50 43 38 35 27 39 60 77 29 24 27
b) Original estimate 37562 107198 111743 139493 88533 47995 52021 52801 97368 144602 130932 66970 62453 187456
c) Now anticipated 40105 115427 121838 153759 101635 49999 52088 56325 102310 156071 137876 91502 84502 252277
d) Cost overrun 2542 8200 10100 14265 13102 2004 68 3524 4942 11470 6944 24532 22048 64821
(Continued)

TABLE 35 : SECTOR-WISE COST OVERRUN OF DELAYED CENTRAL SECTOR PROJECTS (End-March) (Concld.)
(₹ Crore)
Sector / Year 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
10. Power                            
a) Number of projects 40 50 53 44 63 64 57 62 51 47 51 27 22 19
b) Original estimate 105569 137766 135656 124490 164942 171622 199226 227593 199221 199760 222574 107459 78351 71505
c) Now anticipated 110220 152267 150492 142172 193266 208830 230151 274184 244605 270014 291234 171791 134019 126381
d) Cost overrun 4631 14500 14800 17681 28323 37208 30925 46590 45384 70254 68659 64332 55668 54877
11. Railways                            
a) Number of projects 31 34 41 37 35 31 38 29 97 149 157 158 131 143
b) Original estimate 22532 23671 27924 28589 29092 36714 41534 39411 123380 187725 201874 213625 194576 200716
c) Now anticipated 43774 56068 73537 73022 86253 90432 109806 110498 201546 284516 323257 477384 455505 452103
d) Cost overrun 21242 32400 45600 44432 57160 53718 68273 71087 78166 96791 121383 263759 260930 251387
12. Surface transport                            
a) Number of projects 109 93 95 23 104 128 107 48 111 188 155 154 119 204
b) Original estimate 39092 40272 54950 8843 77042 88402 85274 34466 96854 128612 85648 126843 79288 190456
c) Now anticipated 40490 43172 58195 11095 78983 90842 90139 36987 99476 135951 88944 166366 101930 235577
d) Cost overrun 1399 2900 3250 2253 1941 2440 4865 2522 2622 7339 3295 39523 22642 45120
13. Telecommunication                            
a) Number of projects 35 9 5 4 2 2 2 2 3 2 3 2 0 2
b) Original estimate 16628 3856 2935 2018 721 15445 15445 13752 13781 13566 14013 13765 0 24730
c) Now anticipated 17139 4035 2761 1843 721 15345 15345 25082 25118 24904 25343 25125 0 24796
d) Cost overrun 511 200 -174 -175 0 -100 -100 11330 11337 11338 11330 11360 0 66
14. Others                            
a) Number of projects 4 2 1 1 17 18 26 27 27 56 69 35 35 30
b) Original estimate 15728 6938 6395 2494 82662 64808 98854 86365 71272 129505 153112 152255 149433 140099
c) Now anticipated 31872 12796 11609 2494 82662 72118 108617 87106 72514 177485 217166 223574 223853 214865
d) Cost overrun 16144 5858 5214 0 0 7310 9763 742 1242 47980 64054 71319 74422 74766
Total                            
a) Number of projects 271 264 285 209 328 343 327 254 381 567 596 425 354 449
b) Original estimate 299002 425998 475042 437807 575227 528819 594248 588870 717425 930864 988240 761514 645244 877591
c) Now anticipated 361829 500467 569843 538750 699234 644702 720378 727418 877661 1202005 1279714 1266030 1115907 1401211
d) Cost overrun 62827 74469 94801 100943 124007 115883 126130 138548 160236 271140 291474 504516 470663 523620
Notes: 1. Data relate to central sector projects costing ₹100 Crore and above up to 2010. From 2011 onwards data pertain to projects costing ₹150 Crore and above.
2. Projects without date of commissioning are not considered.
3. Cost overrun is taken as the difference between the 'anticipated cost' and the 'original cost'.
4. Surface transport = Road transport + Shipping & ports.
5. Others = Urban Development, Water Resources, Social Justice, Defence Production, Department of Higher Education, Home Affairs, DPIIT, DoNER, and Renewable Energy.
Source: Ministry of Statistics and Programme Implementation, Government of India.