PDF - Minutes of Pre-Bid Meeting - General repairs and external repainting of buildings in Bank’s Main Office Premises, Thiruvananthapuram ()
Date : Nov 26, 2026
Minutes of Pre-Bid Meeting - General repairs and external repainting of buildings in Bank’s Main Office Premises, Thiruvananthapuram

Pre-bid meeting for the captioned work was conducted on November 26, 2026 at 11.00 am at Estate Conference Room in 2nd floor of Main Office Building. List of participants is indicated below:

(a) List of Bank's Officials who attended the meeting

1 Ms. Aiswarya Subramanian Assistant General Manager
2 Shri. Ajmal Meeran Assistant Manager (Tech-Civil)
3 Shri. Jithin Philip Assistant Manager
4 Ms. Jissa Susan Jacob Junior Engineer (Civil)
5 Shri. Vaishnav Unnikrishnan Assistant

(b) List of Contractors' representatives who attended the meeting

SI No Name of the Representative Name of the firm
1 Shri. Shyam S M/s. Speed Enterprises

2. Ms. Aiswarya Subramanian, AGM, welcomed the participants to the meeting and invited queries, if any, from the prospective bidder regarding the captioned tender. The details of queries raised by the Contractor and clarifications / comments of the Bank are tabulated below:

Sl. No. Points of discussion Bank's Clarifications
a Scope of work, Tender timelines, EMD details, material accounting, quality control The vendor was informed that the scope of work covers Main Office Building (from ground floor to third floor level), Annex Building (from ground floor to third floor level), Banking Hall (from ground floor to first floor level), Other small buildings like IFC, Substation, pump rooms, etc. The vendor was informed that they need to submit EMD as mentioned in the tender document before submitting their bids and the last date of submission of bids was December 7, 2026.

The bidder was informed that the work shall be carried out under close supervision of RBI's Engineering team and the contractor shall meticulously follow the tender specifications, while taking up each item of work. There will be zero tolerance for sub-standard materials or deviation from specifications. Delays attributable to the contractor will attract liquidated damages/penalties, as per relevant clauses mentioned in the tender document.

The vendor was informed that they need to provide proper scaffolding and ensure safety of the workers and to provide them with necessary safety equipment for carrying out the work.
b Clarification on CPP Portal It was clarified by the Bank that vendor can bid through the e-tenders link of CPP Portal and the same has been mentioned in the Tender Document. The bidder was advised to quote the rates exclusive of GST in the highlighted cells in BOQ for individual items, and GST shall be added automatically by the system. The bidder was advised to go through the tender document thoroughly before quoting rates in the portal and was also advised to submit EMD well before the cut off time mentioned in the tender document.

Before quoting the rates, bidder was advised to inspect the site and understand the nature and scope of the work.

3. Bidders shall note that all the above clarifications provided by the Bank during the pre-bid meeting along with details indicated in the Tender document shall form part of the Tender/Contract.

4. The meeting concluded at 11:30 am.

Regional Director