| Tender number | RBI/Mumbai Regional Office/Estate/140/24-25/ET/806 |
| Date of publication of NIT | Jan 22, 2025 |
| Nature of work | Replacing the existing wooden windows by UPVC sliding windows, repainting and allied civil works in 06 No. flats (Phase-IX) at RBI Officer’s Colony, Jalada, Mumbai |
| Mode of tender enquiry | E-Tender |
| Type of bidding (single/two bid system) | Two Part Tender |
| Last date of receipt of tender | Feb 21, 2025 |
| Number of tenders received | 5 (Five) |
| Nos. and names of parties qualified after technical evaluation | 5 (Five) 1. M/s Balaji Construction
2. M/s Aakar Shilp
3. M/s Hardik Rajesh Shah
4. M/s Priyanka Enterprises
5. M/s Amit Interior |
| Nos. and names of parties not qualified after technical evaluation | -
|
| Commercial Bid Ranking, if any | 1. M/s Balaji Construction
2. M/s Aakar Shilp
3. M/s Hardik Rajesh Shah
4. M/s Priyanka Enterprises
5. M/s Amit Interior |
| Final Ranking, if any | 1. M/s Balaji Construction
2. M/s Aakar Shilp
3. M/s Hardik Rajesh Shah
4. M/s Priyanka Enterprises
5. M/s Amit Interior |
| Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
| Contract number and date | MRO.ESTT.EST-BY.No.2126/00-06-001/2024-2025 Date Mar 20, 2025 |
| Name of contractor | M/s Balaji Construction |
| Value of contract | ₹37,98,774/- |
| Scheduled date of completion of supplies | Entire work shall be completed in Three (3) calendar months from the 10th day of issue of work order if all 6 flats are handed over at one time or 60 days per flat from date of handing over of one flat, 75 days for 02 flats or 90 days for 03 to 05 flats are handed over at a time. |
| Actual date of start of work | - |
| Actual date of completion of work | - |
| Reasons for delay, if any | - |